I am new to the CNC world and I am trying to convince a local art center to let me build one in their facility. Is there a parts list and estimated price for building a MechMate CNC? How long does it take? Can it cut aluminum?

I am located in upstate New York, and I would like to build one that has a cutting area of 4'x8'.

Thank for your help.

smreish
Wed 02 February 2011, 13:09
Parts list is mostly in the plans and forum.
Yes it can do aluminum, if built with specific reductions and/or geared motors, light alum sheet is suggested, billet is not - but has been done.
On average, the cost to build is ranged from 4500 to 8000 pending motor, spindle and electronics choices.

Average build time is about 6-12 weeks part time. A full time commitment could allow for the machine to be done in about 3 weeks. One very zealous builder completed the project in 2 weeks last year.

Welcome to the forum.

Sean

sawcnc
Fri 04 February 2011, 08:38
Sean,
Thanks for the info. One reason I need a parts list is to provide the board of directors with something more tangible then a price range. A one month build is good as this will be done on a full time basis. I hope I can get a budget together soon. They are allocating their funds for the season and I am not in it.

domino11
Fri 04 February 2011, 10:02
Welcome! :)

Red_boards
Fri 04 February 2011, 17:29
Some of the builders list their steel orders in their personal builds. You might find one that fits. Actually I think there was one posted within the last month.

Then you need motors, interfaces (BOB and Geckos), power supply, computer, miscellaneous wiring and a pile of nuts and bolts (again you will probably find a list in the personal builds with diligent searching).
You'll also need tools and consumables (welding rods, cutting and grinding disks).

I'm sure you can quickly assemble a budget proposal that will fly, as long as you have a reasonably sized "other" category.

BUT before you build you need to devise you own parts list, otherwise you won't fully understand how it goes together (and so where the "borrowed" list might be incorrect for your needs). Also, you need to be pretty on top of your project plan to get it done quickly.

sawcnc
Mon 07 February 2011, 10:19
Red,

I understand that my parts list and budget will be different but I need a place to start. I have never built a CNC machine.

I have access to all the tools and the art center has lots of steel lying around.

Thanks for the tips. I'll report back as things develop.

MetalHead
Mon 07 February 2011, 12:43
I think we may be able to help here if we come up with a list of major table areas like:

1. Plans
2. Laser Cut Parts
3. Electronics (Probably the most expensive part of the build)
4. Base Table Steel
5. Router or Spindle
6. Tools - Welder, Grinder etc.

MetalHead
Mon 07 February 2011, 12:49
Here is a list of the things I have available.

Qty Item ID Description Unit Price Amount
1 BLPK Laser Parts Kit 450.00
1 IB15 Idler Bearing 15.00
1 MPIB Machined Parts 100.00
1 SB4 3 Stop Blocks 40.00
1 DP01 Drive Plates 125.00
1 BC01 Basic Control Box 440.12
1 RB01 Remote Panels Start, Stop, E-stop 135.00
1 MPS01 Motors and Power Supplies 595.00
1 GBD501 PMDX-133(2),126(1),107(1),HDR26RIBBON(2),DB25MtoM(1),Ge cko 203v(5) 1,129.00 (This is a high end setup that has newer items for spindle and indexer control)
1 JZ04 120 ft 4 core wire 118.19
1 JZ08 50ft 8 core wire 78.50


This is a pretty large list of parts and is by no means a complete machine. But it has many of the things needed for the build. You will also need steel for the base table and the guide rails.

I have nuts and bolts if I can just get the time to bag them all up and get them priced.

MetalHead
Mon 07 February 2011, 12:52
Software - don't forget that.

I would say Mach3 and Vetric Aspire if your working to get a complete budget.

sawcnc
Mon 07 February 2011, 18:17
Metal Head,

Thanks! That should give me a pretty good start.

MetalHead
Mon 07 February 2011, 19:30
Be aware you will total out somewhere between 5 and 7 k typically. Mach and Vetrics will add another 2200. I would go long and request $12,000.00 maybe $9,000.00 this will also help you get that needed vac system to suck out the saw dust !!!

Quadro
Wed 09 February 2011, 23:36
Don't forget dust extraction! See Bill's Website (http://billpentz.com/woodworking/cyclone/index.cfm)